Machine fleet management is not limited to inventory and maintenance. For a production manager, the daily question is simpler: what is each machine doing right now, and why is it not producing when it should be? This guide explains which data to track, where it comes from, how to turn it into OEE and which machines to start monitoring first.
Key points
- Good machine fleet management tracks two levels: the raw states sent by the machine (running, stopped, alert, disconnected, counters) and the activities that give them meaning (production, setup, planned or unplanned stop, waiting).
- Data comes from two complementary sources: connected machines (OPC UA, API, IIoT box) and operator reports, which say which production order is running and why the machine stops.
- OEE is calculated from these activities: valuable operating time divided by required time.
- Start with a few machines that matter, validate the data with the teams, then extend to the rest of the fleet.
What is machine fleet management in production?
Machine fleet management covers everything that tells you what state a workshop’s equipment is in and what it delivers. One part belongs to maintenance: inventory, interventions, spare parts. The other belongs to production: real availability, cycle rate, stops, scrap. This second part, machine monitoring, is what this guide covers.
The difference lies in the question asked. Maintenance asks whether the machine is in good condition. Production asks whether it produced what it should have, and if not, where the time went. To answer, you need to follow each machine continuously, not only when it breaks down.
What to track on each machine
Raw states
This is the information a machine can give about itself, without interpretation:
- the state: running, stopped, in alert (alarm), disconnected;
- the counters: number of parts produced, with the time of each change;
- the cycle rate, derived from the counters: the real cycle time, to compare with the theoretical cycle time of the routing.
A raw state says a machine is stopped. It does not say whether it is the lunch break, a setup, a material shortage or a breakdown.
Activities in context
To manage production, every minute of the machine must be assigned to an activity. The context comes from the schedule, the machine’s calendar and what operators report.
| Activity | When the machine is in it | Source of the context |
|---|---|---|
| Production | An operation is in a production step of its routing | Operator report |
| Setup (non-productive activity) | An operation is in another step: setup, preparation | Operator report |
| Unplanned stop | Running operations are paused or interrupted while the machine is open | Interruption report with its cause |
| Automatic stop | The machine stops in the middle of a production step | Connected machine states |
| Planned unavailability | Preventive maintenance, trial, planned absence | Machine calendar |
| Closed | Outside opening hours | Machine calendar |
| Waiting | Machine open and available, but no operation reported | No report |
Waiting deserves special attention. An available machine with nothing to do causes no breakdown, but it often reveals a planning, material or staffing problem.
Where machine monitoring data comes from
Connected machines
Machine data is collected through a connector suited to each type of machine. The most common options are:
- OPC UA, offered by many recent CNC controls and PLCs;
- an API provided by the manufacturer or by machine software;
- an IIoT box, added to an older machine to read a running signal or a counter.
Before choosing, take an inventory of your fleet: brand, CNC control, year, available connection method. Special or older machines often need to be looked at case by case.
Operator reports
A connected machine knows it is running. It does not always know which production order it is producing, whether it is in setup or why it stopped. That information comes from operators, who report on a tablet or a shop floor terminal:
- the start of the operation, each step change (setup, then production) and the end;
- pauses and interruptions, with a cause chosen from a list;
- good quantities and scrap.
For a machine that is not connected, these reports remain the only source. They are enough to track production, setups and reported stops, but not micro-stops or the real cycle rate.

From data to OEE: the calculation method
Once every minute is assigned to an activity, OEE is calculated from the durations. Here is the method used by Seganto, which follows the classic definition:
- Effective time: the duration of production activities.
- Valuable operating time: the time the good parts should have taken according to the routing, that is the number of good parts multiplied by the theoretical cycle time.
- Required time: effective time, plus unplanned stops, automatic stops and setups.
- Opening time: required time, plus planned unavailability and waiting.
OEE = Quality × Performance × Availability = valuable operating time ÷ required time
OOE divides valuable operating time by opening time: it also charges planned unavailability and waiting to the machine.
A performance above 100% means the machine produced faster than the routing’s cycle time. Check the routing or the reported quantities before drawing conclusions.
Organizing machine fleet management: where to start
Connecting the whole fleet at once is rarely a good idea. Data arrives in bulk, nobody checks it and trust disappears at the first wrong figure. A step-by-step approach gives better results.
- Choose a few machines: those that limit the workshop’s throughput, those with the highest hourly cost, or those whose stops cause the most discussion.
- Update their calendar: hours, shifts, planned preventive maintenance. Without an accurate calendar, a closure becomes a stop and OEE is wrong.
- Check routing cycle times. Valuable operating time depends directly on them.
- Define a short list of stop causes with operators: breakdown, waiting for material, waiting for inspection, tool change. A list that is too long does not get filled in.
- Connect the machines that allow it and compare raw states with reports for a few weeks.
- Display the results on the shop floor, then extend to the rest of the fleet once the teams accept the figures.
The checklist to copy for your fleet inventory
| Item | To record for each machine | Example |
|---|---|---|
| Identification | Workshop, type, brand, CNC control, year | Sliding headstock lathe, bar turning workshop |
| Connection | OPC UA, API, IIoT box or none | OPC UA available |
| Available data | States, part counter, alarms | States and counter |
| Calendar | Shifts, hours, planned maintenance | 2 shifts, maintenance on Friday afternoon |
| Routings | Theoretical cycle time up to date or not | To check on 3 items |
| Reports | Entry terminal, stop causes used | Shared tablet, 6 causes |
| Priority | Bottleneck, hourly cost, frequent stops | Workshop bottleneck |
The examples are fictitious: replace them with data from your fleet.
Monitoring live and analyzing afterwards
Monitoring has two uses that do not need the same screens.
Live, the workshop manager wants to see at a glance the stopped machines, the setups running over and the operations that will finish late. A screen on the shop floor lets everyone see the same information.
Afterwards, the production manager and the methods department look for what lowers OEE: which activity weighs the most, on which machine, and whether the trend improves from one week to the next. The OEE of a single day says little. Its evolution over several weeks shows whether the actions taken are paying off.

How Seganto helps monitor a machine fleet
Seganto brings both data sources and the schedule together in the same software:
- Raw data: the states (running, stopped, alert, disconnected) and counters of each connected machine, with history over a chosen period. A connector suited to each type of machine is configured in the resource tree.
- Live monitoring: one card per machine combining operator reports, the schedule, the calendar and machine data. It shows the current step, the counter since the start of the operation, the real cycle time and its deviation from the theoretical one, the expected end and the next item.
- Machine activities: what each machine was doing hour by hour over the last week, the share of each activity, and the quality, performance, availability and OEE rates.
- OEE history: the day-by-day evolution of OEE, OOE, TEEP and their components, per workshop.
- TV screens: live monitoring of selected machines, displayed on the shop floor, alone or in a slideshow with the schedule.
One option also uses machine states to count a machine stopped in the middle of production as an automatic stop, and another uses the machine counter to complete the quantities of running operations. Seganto builds on the machine expertise of Objectis, with more than 20 years of experience. The machine monitoring page presents these features in detail.
Frequently asked questions about machine fleet management
What is the difference between machine fleet management and a CMMS?
A CMMS manages maintenance: equipment, interventions, spare parts. Machine monitoring tracks their production activity: states, cycle rate, stops and OEE. The two complement each other: unavailability planned for maintenance must appear in the machine calendar for OEE to be accurate.
Can you monitor a machine that is not connected?
Partly. Operator reports give production, setups, interruptions with their cause, and quantities. Real-time states, micro-stops, the part counter and the real cycle rate require a connection through OPC UA, an API or an IIoT box.
How many machines should you connect at first?
A few are enough: those that limit the workshop’s throughput or whose stops cost the most. They are used to validate calendars, cycle times and stop causes before extending to the rest of the fleet.
Why are machine states not enough to calculate OEE?
A stop state does not say whether it is a setup, a planned break or a breakdown. OEE needs that context, which comes from the machine calendar and operator reports, as well as the routing cycle times to calculate valuable operating time.
How often should you look at OEE?
States and stops are followed live. OEE is better read over the week and the month, comparing the recent trend with the average, because a single day varies a lot depending on the batches produced.
See monitoring for your machine fleet
Book a demo: together we look at your machines, their connection options and the first indicators to track.
Book a demoDiscover machine monitoring