A full schedule, overtime, slipping lead times: many workshops say they are saturated. Yet when you compare real load and capacity workstation by workstation, the overload is almost always concentrated on a few resources. Here is how to calculate your production load, compare it with your capacity and find where it really gets stuck.
Key takeaways
- Load is the working time required by your production orders; capacity is the time actually available on your workstations.
- The load rate (load ÷ capacity) is calculated workstation by workstation and week by week, never as an average across the whole workshop.
- Real capacity is lower than theoretical capacity: stoppages, setups and absences can easily reduce it by 15 to 30%.
Production load and capacity: what are we talking about?
Production load is the volume of work your orders place on each resource: machines, manual workstations or teams. It is expressed in hours and comes directly from your routings.
Production capacity is the time each resource can actually devote to this work over the same period. This is where the gaps begin: the capacity recorded in the ERP or the spreadsheet is often a theoretical capacity (opening hours × number of workstations), while the shop floor lives with breakdowns, changeovers and absences.
How to calculate production load
For a given workstation and period, the load is the sum of the time needed for each operation planned on that workstation:
The data comes from production orders (quantities) and routings (unit times and setup times). If your routing times are old or padded for safety, the calculated load will be too: this is the first source of error.
How to calculate real capacity
The availability rate can be measured: running time ÷ opening time. Without measurement, people often assume 100%, and that is what makes schedules unrealistic from Monday morning.
Worked example: a workshop with 3 workstations over one week
Take a workshop open 40 hours a week, with one workstation per resource type:
| Workstation | Load | Theoretical capacity | Measured availability | Real capacity | Real load rate |
|---|---|---|---|---|---|
| Machining | 38 h | 40 h | 80% | 32 h | 119% |
| Polishing | 24 h | 40 h | 90% | 36 h | 67% |
| Inspection | 15 h | 40 h | 95% | 38 h | 39% |
Based on theoretical capacity, machining appears to be loaded at 95%: tight but feasible. With real availability, it is at 119%, or about 6 hours of excess work this week. Polishing and inspection, on the other hand, have spare capacity. The workshop is not saturated; only one workstation is.
The right reflex: look at the real load rate per workstation and per week. An average across the workshop (73% here) completely hides the problem.
Overload or poor distribution?
When a workstation exceeds 100%, three questions tell you whether capacity is really lacking:
- Can the work be moved in time? Some production orders often have a need date later than the planned date.
- Can the work be moved to another resource? An equivalent machine, an alternative routing or a multi-skilled operator.
- Is the workstation losing time? If its availability is low, the priority is to recover hours (setups, minor stoppages) before adding more.
If the answer is no to all three, the overload is real and it is a true bottleneck.
Identifying bottlenecks
The bottleneck is the resource whose capacity limits the output of the whole workshop. It can be spotted by three signs: a real load rate persistently above 90%, a queue building up in front of the workstation, and downstream workstations waiting.
An hour gained on the bottleneck is an hour gained for the whole workshop. An hour gained elsewhere does not change the delivery lead time. That is why improvement efforts (shorter setups, preventive maintenance, staggered shifts) should focus on it first.

The hidden cost of safety margins
For lack of visibility, margins get added: inflated routing times, buffer days in the schedule, lead times announced “just in case”. Each margin is reassuring, but they add up. The result: longer throughput times, less competitive lead times and capacity that looks occupied when it is not.
Measuring actual times lets you replace these margins with reliable values, workstation by workstation. It is often the quickest gain, with no investment in machines.
Moving from a one-off calculation to continuous tracking
A load calculation in a spreadsheet gives a snapshot at a given moment. As soon as an urgent production order arrives or a machine stops, the snapshot is wrong. For the load to stay accurate, you need to:
- plan at finite capacity, that is, without exceeding what each workstation can absorb;
- feed back actual progress from the shop floor, to recalculate the remaining load;
- measure machine availability, so that the capacity used in the schedule is the real capacity.
This is the role of scheduling software connected to the shop floor. With Seganto, the load of each workstation is recalculated from production orders, routings and declared progress, and finite capacity planning shows overloads before they turn into delays. Combined with machine supervision, the capacity used is the one your machines really deliver.

Frequently asked questions about load and capacity
What is the difference between production load and capacity?
Load is the working time required by orders and production orders. Capacity is the time resources can provide over the same period. The two are compared to know whether the schedule is achievable.
How do you calculate a workstation’s load rate?
Load rate = load ÷ real capacity × 100. Above 100%, the workstation cannot absorb the planned work; between 85% and 100%, it has almost no margin left for urgent orders.
Should you plan at 100% of capacity?
No. Aiming for 85 to 90% of real capacity leaves room for urgent orders and contingencies, without degrading lead times already promised.
Can you calculate production load in Excel?
Yes, for a one-off snapshot: the formulas above are enough. The spreadsheet reaches its limits as soon as production orders change every day, because the load then has to be recalculated with actual progress. See also our article on production planning in Excel.
In summary
Knowing your production load means comparing, workstation by workstation and week by week, the time required by production orders with the time actually available. This simple calculation often changes the diagnosis: less general saturation, more identified bottlenecks, and safety margins that can be reduced with reliable data.